B. Braun Simulation FTS
B. Braun Simulation FTS
B. Braun Simulation FTS
B. Braun Simulation FTS
B. Braun Simulation FTS
B. Braun Simulation FTS
Info

The logistics production supply processes were also analyzed as part of an extensive modernization, expansion and renovation project at B. Braun Melsungen AG in Berlin. Focusing on possible approaches to improvement, as well as safeguarding future requirements, one of the questions to be dealt with was whether it is possible to use driverless transport systems (AGVs). A simulation was used to evaluate possible routes, points of conflict with oncoming traffic, and the number of necessary vehicles and capacitive borderline situations.

Technical parameters:    

6 AGV vehicles, 2 battery charging stations, 9 conveyor technology connections to high-bay warehouses and production lines, 25 manually operated transfer points

Client
B. Braun Melsungen AG, 34212 Melsungen
Period of service
01.2021 till 03.2021
Services
Simulation